Storage and handling
- Protect pipes and fittings from sunlight (UV), weather and dirt.
- Store pipes straight and supported along their full length.
- Do not drag pipes or throw them off vehicles.
- Below +5 °C impact sensitivity increases; handle with care.
- Keep away from areas where solvents, paints or adhesives are stored.
Cutting and preparation
- Cut the pipe square with PPRC pipe shears or a pipe cutter and deburr.
- Chamfer the pipe end, clean the welding surfaces and mark the insertion depth.
- Never cut threads into plastic parts; use fittings with metal threaded inserts and seal threads with PTFE tape or a suitable sealant.
- Do not heat or bend pipes with an open flame.
Fusion welding
Pipe and fitting are heated on the 260 °C heating tool and joined without twisting. For heating, joining and cooling times by diameter, see the detailed chart: Fusion welding times
Support (clip) spacing
On horizontal runs the clip spacing depends on pipe diameter, pipe series and fluid temperature. Higher temperature means shorter spacing.
| Outside diameter d (mm) | 20 °C | 40 °C | 60 °C | 80 °C |
|---|---|---|---|---|
| 20 | 90 | 80 | 70 | 65 |
| 25 | 95 | 95 | 80 | 75 |
| 32 | 110 | 105 | 95 | 80 |
| 40 | 120 | 115 | 100 | 95 |
| 50 | 135 | 125 | 115 | 100 |
| 63 | 155 | 145 | 130 | 115 |
| 75 | 170 | 160 | 145 | 125 |
| 90 | 180 | 170 | 160 | 135 |
| 110 | 200 | 190 | 175 | 155 |
- For vertical runs the spacing in the table may be multiplied by 1.3.
- Thinner-walled (SDR 11) pipes need shorter spacing, fibre-reinforced pipes allow longer spacing; use the table of the pipe manufacturer.
- Metal clips must have a rubber lining where they touch the pipe.
Thermal expansion and expansion allowance
A temperature change makes a PPRC pipe change length: ΔL = α · L · ΔT (ΔL in mm, L in metres, ΔT in K). For unreinforced PPRC take α ≈ 0.15 mm/(m·K) (1.5·10⁻⁴ K⁻¹). Some manufacturers design with 0.12; glass-fibre reinforced pipes are around 0.03–0.035 mm/(m·K).
| Pipe length L | ΔT = 20 K | ΔT = 40 K | ΔT = 60 K |
|---|---|---|---|
| 1 m | 3 | 6 | 9 |
| 5 m | 15 | 30 | 45 |
| 10 m | 30 | 60 | 90 |
| 20 m | 60 | 120 | 180 |
Expansion is taken up by a change of direction (flexible arm), a U-shaped expansion loop or a compensator. The flexible arm length is Ls = k · √(d · ΔL), where k is a material constant (e.g. k = 20 for PPRC in one manufacturer manual).
Example: d = 32 mm, L = 10 m, ΔT = 40 K → ΔL = 0.15 × 10 × 40 = 60 mm; Ls = 20 × √(32 × 60) ≈ 876 mm.
- Fixed points lock the pipe; sliding points allow axial movement. Place sliding clips so they do not block expansion.
- Expansion loop width: Lk = 2 · ΔL + 150 mm and Lk ≥ 10 · d.
- On vertical risers pay special attention to fixed points; prefer fixed clips over sliding clips.
- Cold bending at +15 °C; minimum bending radius 8 · d for Ø16–32 mm.
Pressure test
Pressure testing follows local regulations and the project specification. Example procedure from a manufacturer manual:
- Fill the line with water no sooner than 1 hour after the last weld, from the lowest point, and bleed the air.
- Keep the system at operating pressure for at least 12 hours.
- Raise to 15 bar test pressure; the test lasts 60 minutes.
- The maximum allowed pressure drop is 0.2 bar; if higher, find and repair the leak and repeat the test.
- Keep test sections to about 100 m and record the results in a test report.
Sources
Values were compiled from published documents based on the standards below and cross-checked against each other. Full standard texts are paid, so manufacturer catalogues declaring conformity to them were also used.
- Wavin – Pilsa piping systems technical and installation manual (support spacing, expansion, pressure test)
- Peštan – Technical catalogue, pipes and fittings DN16–630 (tube geometry table, expansion coefficient, support spacing)
- SIMONA – work.info Welding: heated element socket welding guide values, DVS 2207-1 and 2207-11
- Uplast – PPRC pipe and fitting systems technical catalogue (wall thickness table S5–S2, application classes)
This page is for information only. The project specification, local regulations and the instructions of the pipe and fitting manufacturer always take precedence.